"CDOT has communicated to the town that the Rislenda and Riverview developers collectively need to come up with $1,900,000 to make improvements that are a total of 8,000,000 at the interchange," Jim Mann told Silt trustees on June 8, 2026, according to Citizen Portal's account of the meeting.

That request arrived late. It was tied to access control permitting, and it came after both projects were already well into the town's approval process. Since then, the main question at the I-70 Exit 97 interchange has been who carries the cost of making it work, and when. The answer will shape when new commercial space opens on the south side of the interstate. Anyone underwriting a lease, a pad site or a land position near the interchange should treat the town's negotiation with CDOT as the real construction schedule.

A permit late in the process

Silt's own approvals don't decide whether the two developments can connect to the state system. That depends on CDOT's access permit, and the obligations came through that permit. CDOT assigned two groups of work at the interchange: signalization or roundabout improvements, and ramp improvements. Both are tied to the two developments that triggered them.

The issue was already slowing projects in the spring. At a March 3, 2026 Planning and Zoning hearing, the applicant team described repeated rounds of work with CDOT. They said recent changes in CDOT's expectations could shift who pays, and commissioners asked for clearer traffic answers before final approval, as Citizen Portal reported. The commission continued the Riverview preliminary plan to April 7 to resolve engineering, traffic study, wetland and parkland questions.

The interchange cost is a real friction point for investors. Land use approvals can move ahead while an infrastructure bill from a separate agency is still being negotiated.

Two projects share one bill

Both developments sit next to the interchange south of I-70, on opposite sides of County Road 311.

Riverview Mixed UseRislende
Location1421 River Frontage Road, south of River Frontage Road and west of CR 31154 311 County Road, south of I-70 and east of CR 311
SiteFive lots on 15.215 acres51.14 acres
Program on fileTraffic study assumes about 198 multifamily units, two 2,800 sq ft drive-through restaurants and about 23,700 sq ft of retailPUD sets a 10,000 sq ft minimum commercial buildout on Tract 3
Town approvalsSketch plan, Resolution 48, Series 2025; preliminary plan, Resolution 20, Series 2026Improvements agreement, amended annexation and final plat, Resolutions 18 through 20 of 2025
Applicant of recordCunningham Development Company; owner Red Horse, LLCAugust Group LLC, doing business as Rislende; owner Silt 70 LLC

The Riverview traffic study methodology places the site about 500 feet east of the interchange. At that distance, any new trip from the drive-throughs or the retail goes through the ramps and intersection CDOT wants rebuilt. CDOT stated the $1.9 million as one figure for both developers together. For an investor, that means each project's infrastructure cost is bound up with how the other one's share gets settled.

Why the town stepped in

If two developers each built their share of an interchange on their own schedules, the result would be partial improvements built at different times. Silt chose a different approach. On July 13, 2026, trustees voted unanimously to authorize staff to negotiate a three-party partnership with CDOT and the two developers, as Citizen Portal reported. The discussion included a possible town contribution and ways to recover costs. Back in June, staff and commissioners had already discussed spreading the cost across more developers and using other financing tools.

By September 14, town counsel described a plan for the town to contract for selected off-site improvements and then recover costs from the developers, so the work would not be built piecemeal. According to Citizen Portal's report on that briefing, CDOT had signaled that under the proposed agreements the town might carry the risk of cost overruns. Counsel also said, "CDOT is anticipating that the budget for these two improvements is actually gonna go down by a meaningful amount," with a refined estimate still to come.

That arrangement shifts the uncertainty. If the town manages construction and carries the overrun exposure, the developers' cost becomes a recovery obligation rather than a construction bid that could grow. That makes their projections more predictable. It also means the town's own budget now has an interest in how the interchange turns out, at the same time trustees are preparing to adopt a budget on December 14.

Construction is planned through 2028

The interchange has been on the town's list for years, and the current package is the latest phase. Here is how the record shows it developing:

  1. May 2023. The town announced a $1,066,000 Highway Safety Improvement Program grant to improve the eastbound Exit 97 on-ramp, funded 90% federal with a 10% state match. The Post Independent described that ramp as too short and in poor condition.
  2. December 2025. A draft CDOT Region 3 plan set aside $7 million in its first four years and $16 million in its final six years for interchange improvements at both Silt's Exit 97 and New Castle's Exit 105, as the Post Independent reported.
  3. June 2026. CDOT asked the Riverview and Rislende developers for about $1.9 million toward an interchange package of roughly $8 million.
  4. July 2026. Trustees authorized negotiations on a three-party partnership.
  5. August 2026. The board's August 24 agenda listed a CDOT agreement on Exit 97 improvements and developer contribution agreements for executive session. On August 31, a special meeting agenda listed an amendment to RockSol Consulting Group's design contract for an I-70 bike and pedestrian overpass.
  6. September 2026. CDOT's plan called for limited work in 2027 and major construction in 2028.
  7. November 2026. The November 9 board agenda put "Agreements for Improvements to I-70 Interchange" back into executive session.

The 2023 grant and the 2025 draft plan show that CDOT has had Exit 97 on its list for some time. Treat the draft plan figures as planning numbers. They cover two interchanges, and the draft predates the current negotiation. For a business deciding when to open near the interchange, 2028 is the year that matters.

Rislende's commercial requirement has no start date

Rislende's commercial piece shows why the interchange schedule matters so much for tenants. At the June 2025 Planning and Zoning review, Director Nicole Centeno presented the applicant's final proposal for Tract 3. It removed 24 residential units, about 20,000 square feet, and kept the full tract with August Group as Rislende's commercial hub. Housing is still allowed on Tract 3, but only above ground-floor commercial or office space. The PUD guide sets a 10,000 square foot minimum for commercial buildout, and the proposal ruled out any schedule for it in these words:

There cannot be any timeline or mandate to artificially force the timing or sequencing of any amount of commercial at any point in time.

The town secured a minimum amount of commercial space but not a date for it. Without a deadline, the commercial hub gets built when the developer's numbers work. Those numbers now include a share of the interchange bill and a CDOT construction schedule that reaches into 2028. In the same review, applicants agreed to move some questioned uses, light manufacturing among them, from use by right to special use. That gives the town and the HOA a say in which businesses fit there.

Riverview's figures should be read the same way. Two drive-through restaurants and about 23,700 square feet of retail are the assumptions its traffic study was built on. They are not a leasing plan, and the drive-through traffic is a big part of why CDOT focused on the ramps.

What to ask before signing near the interchange

A restaurant owner looking at a future pad on River Frontage Road, or a landlord pricing space on the north side of the interchange, can find most of the useful information in public meeting records:

  • The cost split. CDOT's $1.9 million request was made to the two developers together, so ask how a developer's own share has been settled before trusting their delivery date.
  • The refined estimate. A lower CDOT number would reduce the amount any party has to recover, whether that is the town or the developers.
  • The 2027 work window. Limited work in 2027 means some construction will reach the interchange before the major 2028 phase. Retailers who depend on easy access off I-70 should plan their opening around both years.
  • The board calendar. Trustees meet November 23 and December 14, when the budget is scheduled for adoption, with January 11, 2027 listed as tentative.

This post is general information about a public process, not legal, tax or financial advice. Anyone weighing a lease, purchase or development agreement should review their own situation with an attorney, accountant or lender.

If you're weighing a lease, a pad site or a land position around Exit 97, C&E Group can help you model it against the interchange schedule, from rent-to-sales on a future frontage-road space to timing for an investor's hold. Connect with the C&E Team.

Read More Articles

Work With Us

At both ends of the street, are entrepreneurs moving towards each other. Entrepreneurs (landlords) purchase commercial buildings. Entrepreneurs (tenants) fill commercial buildings.

Contact Us
Contact Us